Delivering solar across a live leisure portfolio demands meticulous planning. Across every site, electrical shutdowns are scheduled out of hours, meaning clubs continue to run day to day with no disruption to their members.
Each club presents its own constraints, and the delivery approach is adapted accordingly. At one site located on a busy industrial estate, deliveries were routed via a rear service road and coordinated with both the estate’s management and the club to ensure access was maintained at all times. At tighter sites with limited parking, delivery dates were communicated well in advance and scheduled for off-peak periods to minimise impact on members.
Attention to detail extends to the finished installation. Cable tray drops from roof level are colour-coded to match the building façade, limiting the visual impact of each system, and panels are cleaned on completion, so every installation is handed over performing at its best.
This repeatable, site-sensitive delivery model provides a proven template as the rollout continues across the wider portfolio.